Division Street Project Updates

July 19, 2017 

Phase 2 temporary road closure of Adams Avenue.

The City of Bemidji and ISD #31, along with Karvakko and Reierson Construction Inc. will begin a temporary road closure of Adams Avenue, just North of Division Street, as part of Phase 2 of the Division Street Utility Extension Project. Beginning Thursday July 20th, 2017 through Saturday July 22nd, 2017, traffic on Adams Avenue will be detoured using 15th Street, Division Street, and Irvine Avenue. Eastbound and westbound traffic on Division Street will remain open during this work.

Posted below is the detour to be used during this phase of construction. 

July 12, 2017

The City of Bemidji and ISD #31, along with Karvakko and Reierson Construction Inc. will begin construction on Phase 2 of the Division Street Utility Extension Project, Monday July 17th, 2017. 

Phase 2 of the project is scheduled to be completed by August 11th, 2017, depending on weather conditions. 

This project will involve bituminous removal, water and sewer main and service installations, bituminous paving, and turf establishment. During construction of Phase 2, the intersection of Division Street and Adams Avenue will remain a temporary 4-way stop. Traffic along Adams Avenue, north of the intersection with Division Street, will be shifted to the east but will remain open to two-way traffic. A temporary closure of the intersection of Division Street and Adams Avenue will take place during construction of Phase 2 to install water main across the intersection, a notice of the intersection closure will be given prior to construction. All High School entrances will remain open for the duration of the project. 

June 1, 2017

Individuals needing to access the High School are asked to use the west entrance from Adams Avenue between now and completion of Phase 1.

June 1, 2017

The City of Bemidji and ISD #31 along with Karvakko and Reierson Construction Inc. will begin construction on Phase 1 of the Division Street Utility Extension Project. The project will begin on Tuesday June 6th, 2017.

Phase 1 – Division Street between Adams Avenue & US HWY 2

Phase 2 – Adams Avenue (North of Division Street)

Phase 3 – Division Street between Adams Avenue & Becida Road.

Phase 1 of the project is scheduled to be completed by July 14th, 2017 depending on weather conditions.

This project will involve the removal and replacement of bituminous pavement, aggregate material, concrete curb & gutter, and turf establishment. During construction of Phase 1, Division Street, between Adams Avenue and US HWY 2, will be closed and traffic will be detoured (see the attached exhibit drawing for detour routes).

Phases 2 & 3 will incur minor traffic delays, but should allow two way vehicular traffic during construction. Project completion, including Phases 1-3, is scheduled for September 22nd, 2017.

Residents should be able to access their driveways during most of the construction, although there will be short time periods where this will not be possible. The project inspectors and the contractor will try to insure that driveways are accessible in the morning and by the end of the day and will be in contact with the residents impacted by these issues. If you have any issues or problems getting into your driveway please do not hesitate to call one of the project inspectors/foreman listed below.

Travis Reierson – Reierson Construction Foreman – 218-368-6277

Andy Crotty – Karvakko Inspector – 218-556-2259

Sam Anderson – Karvakko Project Manager – 218-766-8615